OEE & loss explorer

See how your equipment performs—and where productive time goes.

Exclude only time when production was not intended. Include changeovers and other stops within planned production. Do not subtract the same stop twice.

Fictional example · replace every input with your measurements.

Method, boundaries & sources

Availability = run ÷ planned time. Performance = total ÷ (ideal rate × run time). Quality = good ÷ total. OEE = ideal time for good output ÷ planned time. Unavailable factors are shown as —.

Losses use equivalent minutes: recorded stops; run minus ideal time for all output; ideal time for rejects/rework; and ideal time for good output. They sum to planned production time.

One product, one equipment boundary, one period. For different ideal speeds, save separate runs; do not average their OEE percentages. Use Staffing for labour workload and service capacity.